Project

Zhan Jiang Sea area HDD Crossing Project

  09/12/2562
  • HDD Brief  Information: 4060 m /159mm/ Steel Pipe/  Gravel, sand Stratum
  • Project Information: Zhanjiang Guangdong Province, China
  • HDD Rig: GD-6000L(Maximum pullback force is 600 tons)
  • GD-5000L(Maximum pullback force is 500 tons)
  • Duration:2018/12/20- 2019/01/29, total 39 days