Zhan Jiang Sea area HDD Crossing Project
09/12/2562
- HDD Brief Information: 4060 m /159mm/ Steel Pipe/ Gravel, sand Stratum
- Project Information: Zhanjiang Guangdong Province, China
- HDD Rig: GD-6000L(Maximum pullback force is 600 tons)
- GD-5000L(Maximum pullback force is 500 tons)
- Duration:2018/12/20- 2019/01/29, total 39 days