-Project Brief Information: The pipeline runs from Link Line SARABURI Pump Station to receipt facilities located around KP 52 of the NBPT Pipeline, to a new station to be constructed named NBPT Link Line Receiving Station (LLRS).The pipeline will be 12-inch diameter. The new buried pipeline sections of NBPT pipeline diversion to the NBPT Link Line Receiving Station shall be 14-inch diameter matching the existing NBPT pipeline to which it connects.
-Scope of work: Pipeline detailed engineering;Procurement of equipment and materials for project;Installation of about 52KM pipeline includeing open-cut around 27KM and HDD 25KM.
-Project location: Thailand
-Main resources input:3 welding teams;4 HDD teams (8 rigs)
-Con. Duration:2024/11/15 to 2026/9/14 (in executing)
-Owner: BPT;Main Contract:TTEC