Brief Information: MEA-30 Pieces PE pipeline HDD Crossing, 180mm*30, Soil Stratum, 370m, in BKK.
Work Location: BKK, Thailand
HDD Rig: GD-2200L (220 Tons)
Work Duration:2020/10/25-2020/12/27, total 63 days
2021/02/21-2021/04/06, total 45 days