Thailand MEA-30 Pieces PE Pipes HDD Crossing

  09/09/2565

Brief Information: MEA-30 Pieces PE pipeline HDD Crossing, 180mm*30, Soil Stratum,  370m, in BKK.

Work Location: BKK, Thailand

HDD Rig: GD-2200L (220 Tons)

Work Duration:2020/10/25-2020/12/27, total 63 days

                       2021/02/21-2021/04/06, total 45 days