HDD Brief Information: 1400m /42 inch/ Steel Pipe/ Gravel, sand and Rock Stratum
Project Information: Rayong Gulf area, 5TP Project in Thailand
HDD Rig: GD-6000L, The maximum pullback force is 600 tons
Con. Duration:2018/10/15- 2019/02/18, total 95 days
Owner: PTT , Contractor: SINOPEC
This is the longest and biggest HDD crossing in Thailand till now!