5TP HDD7 Project in Thailand

  09/12/2562
  • HDD Brief  Information: 600m /42 inch/ Steel Pipe/  Granite Rock Stratum
  • Project Information: Chonburi , 5TP Project in Thailand
  • HDD Rig: GD-6000L, The maximum pullback force is 600 tons
  • Duration:2018/3/18- 2019/06/15, total 89 days
  • Owner: PTT , Contractor: SINOPEC